Sagheer Avenue G+6

Project Overview

A commercial G+6 building project in Pakistan, covering shop drawing review, technical documentation, and coordination of multiple trades across six floors.

Duration

2020 – 2022

Value

PKR 81.4 Million

Role

Civil Site Engineer

Challenge

Six floors, multiple trades, one sequence:

Multi-Trade Sequencing

Structural, electrical, and finishing subcontractors all needed to move through six floors without overlapping into each other's work.

Drawing-to-Site Accuracy

Keeping site work aligned with approved shop drawings across a building tall enough that small early misalignments compound floor by floor.

The Approach

Documentation-first coordination, floor by floor:

Shop Drawing Review Before Execution

Cross-checking structural and electrical layouts at the review stage, before construction reached each floor.

RFI and Technical Query Management

Raising and tracking RFIs and technical queries early enough to keep floor-by-floor progress from stalling.

Weekly Progress Reporting

Structured weekly reporting to keep the client and consultant aligned on real site status, floor by floor.

Execution

Where Strategy Meets Execution

Reviewed and submitted shop drawings and material submittals for each floor

Sequenced structural, electrical, and finishing trades across six floors without idle time

Raised and tracked RFIs to keep floor-by-floor progress on schedule

Prepared and presented weekly progress reports to client and consultants

Results & Impacts

Measured Results & Project Impact

Real site execution is defined by how quickly problems are controlled—not how well plans are written.

Key Insight

Key Insight

On a mid-rise commercial build, catching drawing misalignments at the review stage is far cheaper than catching them on site, floor by floor.

Clash-Free Structural-Electrical Coordination

No structural-electrical conflicts reached construction due to early shop drawing review.

On-Schedule Floor Handover

Each floor progressed through structural, electrical, and finishing stages without cross-trade delay.