EBARA Pumps Expansion

Project Overview

An active industrial expansion project in Dammam, Saudi Arabia, involving complex excavation around dense underground utilities and ongoing civil-MEP coordination.

Duration

2025 – Present

Value

SAR 6.6 Million

Role

Project Engineer

Challenge

Execution is complicated by what's already underground:

Dense Underground Utilities

Excavation routes cross a dense network of existing underground utilities, leaving little margin for error.

Live Industrial Site

Work is coordinated around an active industrial facility, where disruption to existing operations isn't an option.

The Approach

A coordination-first strategy, built around clash prevention:

Multi-Discipline Clash Detection

Cross-checking civil, mechanical, and electrical drawings before excavation reaches each zone, not after.

Phased Excavation Planning

Sequencing excavation zone by zone around confirmed utility locations rather than working the full footprint at once.

Continuous Consultant Coordination

Fast turnaround on technical queries and RFIs to keep excavation decisions moving without delay.

Execution

Where Strategy Meets Execution

Led clash detection across architectural, structural, electrical, and HVAC drawings

Coordinated civil and MEP scopes across active excavation zones

Managed monthly progress reporting, including submissions to MODON

Results & Impacts

Measured Results & Project Impact

On an active industrial site, the real work is preventing conflicts before they reach the ground — not resolving them after.

Key Insight

Zero Utility Strikes

No underground utility conflicts during excavation to date, not only utility, but also drainage pipes, domestic and industrial water pipes.

Clean Multi-Discipline Coordination

Civil and MEP scopes progressing without cross-discipline rework.

On-Schedule Progress

Project tracking against the approved schedule as of 25th July 2026.